Q4 is busy. You’re watching sell-through, chasing inbound shipments and trying to stay in stock through December. So the Q1 purchase order slips to “next week.” However, if you source from China, the order you place in November decides whether you’re in stock in March. Planning your Chinese New Year inventory is November work, and in 2027 that work has to happen earlier than it did last year.
Here is how we would plan it: the dates, a calendar that runs backward from the holiday, how much extra stock to order, and where to hold it so you avoid both stockouts and Amazon fees.
Chinese New Year inventory: the dates that matter for 2027
Chinese New Year 2027 falls on Saturday, February 6, 2027. The official holiday lasts about 8 to 9 days. However, the official holiday is not the part that hurts.
Industry guides say factories commonly stop work in mid-to-late January. After the holiday, full capacity often returns only between late February and mid-March. So the disruption runs for weeks on either side of the holiday. These ranges are typical, not guaranteed, and your supplier’s dates may be different.
There is one more catch. Chinese New Year 2027 falls 11 days earlier than it did in 2026. As a result, last year’s timeline is too late. If you copy it, every step lands late.
Work backward from February 6
The simplest way to plan Chinese New Year inventory is to start at the holiday and work backward. Here is the timeline we would use:
- October to mid-November: confirm dates. Ask every supplier for its shutdown and restart dates, in writing. If you haven’t done this yet, do it this week.
- By the end of November: place the PO. Industry guides recommend committing Q1 and spring orders by about the end of November 2026, before the factory’s pre-holiday production slots fill up.
- December: production. Our rule of thumb is about 30 days of production. So an order placed at the end of November is in production through December.
- January: inspect and ship. Goods need to be inspected and ready for pickup before the factory stops, which can be as early as mid-January.
- February: the closure. Production stops. The stock you already have, on hand and in transit, has to carry you.
- March: the ramp. Factories come back gradually, so new orders take longer than normal.

How a March stockout happens
Here is a common pattern in the industry. A brand is deep in Q4 and sends its spring PO in mid-December. By then the factory’s pre-holiday slots are full. So production slips into January, the factory shuts down before the order is finished, and the goods sit until it restarts. Meanwhile, the brand sells through what it has in February. Then it runs out in March, waiting on an order it thought it had placed in time.
The fix is simple: the PO has to go in before the factory fills up. That is why we treat the end of November as the real deadline, not February 6.
How much extra stock to plan
This is the part of Chinese New Year inventory planning that most sellers guess at. Industry guides suggest planning roughly 4 to 6 extra weeks of delay on any order that spans the closure. For example, here is what that looks like in units for a hypothetical SKU (not a client):
- Daily sales: 40 units a day.
- Normal lead time: 60 days. That’s our rule of thumb of about 30 days of production plus about 30 days of shipping. Sales during the lead time: 40 x 60 = 2,400 units.
- An order that spans Chinese New Year: Add about 35 days of delay, which is inside the 4 to 6 week range. That makes 95 days, so you need 40 x 95 = 3,800 units.
- The difference: 1,400 units.

Those 1,400 units are the closure showing up in your order quantity. They are not overstock. They are the sales you’ll make while the factory is closed and ramping back up. Without them, you sell out early and wait.
Where to hold the buffer without paying for it twice
Ordering 3,800 units doesn’t mean sending 3,800 units to FBA. In fact, there are two ways to overpay for a buffer. Send it all to FBA, and you pay to store weeks of stock that won’t sell yet. Keep FBA too thin, and you risk Amazon’s low-inventory-level fee. A good Chinese New Year inventory plan avoids both.
Know the 28-day rule
The low-inventory-level fee is based on historical days of supply. It applies only when both your short-term (30-day) and long-term (90-day) historical days of supply are below 28 days. We explain how it works in our post on Amazon low inventory fees.
Because both numbers must be under 28, a brief dip is usually not the problem. However, running low for a long stretch through February and March can pull both below 28. That is what a poorly planned Chinese New Year looks like.
Split the stock
Here is how we would split the stock for the example SKU:
- FBA: roughly 30 to 60 days of supply. At 40 units a day, that’s 1,200 to 2,400 units. That keeps you above the 28-day threshold without filling FBA with stock that will sit.
- Upstream: the rest. Hold it in AWD or a 3PL. Amazon Warehousing and Distribution is Amazon’s bulk storage, and it can automatically replenish FBA.
- Feed FBA in waves. Send smaller shipments every few weeks based on actual sales, not on the forecast you made in November. If a SKU sells faster than expected, send the next wave sooner. If it slows, the stock waits upstream.
A pre-holiday checklist for your suppliers
Your Chinese New Year inventory plan is only as good as the dates behind it. Get these dates from every supplier, in writing. A quick “no problem” in a chat thread is not a plan.
- Shutdown date. The last day the factory is producing before the holiday.
- Last cargo-ready date. The last day your goods can be finished, packed and ready to leave.
- Inspection date. Quality risk is highest in the pre-holiday rush and again as the factory ramps back up after the holiday. So book the inspection before the cargo-ready date, and plan to check the first production run after the break too.
- Restart date. Ask when the factory reopens and when it expects to be back at full capacity. Those are often different dates.
Then compare those dates with your timeline. If something doesn’t line up, you want to find out in November, while there’s still time to fix it.
Get your Q1 plan checked
Q4 won’t slow down, and that is exactly why the Q1 order gets missed. If you want a second set of eyes, book our free Storage Costs Audit. We’ll look at your Q1 plan, your stock levels and your storage costs, and show you where your Chinese New Year inventory plan needs work while there’s still time to place the order.
Related guides
- Low Inventory Fees: The Storage Fee Nobody Budgets For
- Drip Feed Inbound: Keep Amazon Storage Near 2.6% of Sales
- Q4 Storage Fees: Hold 60 Days of Stock Without Overpaying
- AWD to FBA Transfer: What to Do When a Container Runs Late
- AWD Auto-Replenishment: The Settings That Keep FBA in Stock Through Peak and Q1
